Todmorden Moor

5 turbines · operational · West Yorkshire

Wind farm facts

StatusOperational
County / regionWest Yorkshire
Turbines5
Installed capacity12.3 MW
Turbine capacity3 MW
Tip heightnot recorded
Operator (or applicant)Todmorden Moor Wind Farm Ltd
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

1999 2001 2003 2005 2007 2009 2011 2013 2015 Scheme REPD 4419 Permission expired April 2000 Application submitted September 2010 Permission granted April 2011 Under construction February 2013 Operational September 2014 Scheme REPD 3483 Application submitted February 2007 Refused November 2007

From application to operation, this scheme took about 4 years.

The register links a second scheme on this site (REPD ref 3483, Revised): 5 turbines · 3 MW each · applicant Coronation Power. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4419.

What the register tells us

The application was determined in about 7 months. Construction to first power took about 19 months. A planning permission on this site expired in April 2000. The scheme has been operating for about 12 years. That works out at 2.46 MW per turbine on average.