13 turbines · revised · Highland
| Status | Revised |
|---|---|
| County / region | Highland |
| Turbines | 13 |
| Installed capacity | 39.1 MW |
| Turbine capacity | 3 MW |
| Tip height | 125 m |
| Operator (or applicant) | Infinergy |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
The register links a second scheme on this site (REPD ref 4420, Operational): 13 turbines · 3 MW each · 125 m tip height · applicant Infinergy. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4267.
The application was determined in about 48 months. The register records a refusal in August 2010 before the scheme progressed. Permission was ultimately granted on appeal in June 2013. A planning permission on this site expired in June 2011. That works out at 3.01 MW per turbine on average.
See all wind farms in Highland.