Torrance Farm

3 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines3
Installed capacity9 MW
Turbine capacity3 MW
Tip heightnot recorded
Operator (or applicant)Future Spectrum Ltd
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2009 2010 2011 2012 2013 2014 Project timeline Application submitted August 2010 Permission granted February 2011 Under construction February 2013 Operational December 2013

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3799.

What the register tells us

The application was determined in about 6 months. Construction to first power took about 10 months. The scheme has been operating for about 13 years. That works out at 3 MW per turbine on average.

Nearby

See all wind farms in Strathclyde.