Torrance Farm Wind Park Extension

2 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines2
Installed capacity5.7 MW
Turbine capacity3 MW
Tip heightnot recorded
Operator (or applicant)Capital Dynamics
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 Project timeline Application submitted March 2012 Permission granted July 2012 Under construction December 2014 Operational June 2015 Permission expired July 2019

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4085.

What the register tells us

The application was determined in about 4 months. Construction to first power took about 6 months. A planning permission on this site expired in July 2019. The scheme has been operating for about 11 years. That works out at 2.85 MW per turbine on average.

Nearby

See all wind farms in Strathclyde.