Tow Law Wind Farm

3 turbines · operational · County Durham

Wind farm facts

StatusOperational
County / regionCounty Durham
Turbines3
Installed capacity2.6 MW
Turbine capacity0.9 MW
Tip heightnot recorded
Operator (or applicant)RWE npower
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 Project timeline Application submitted July 1999 Permission granted June 2000 Operational December 2001 Permission expired June 2017

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2586.

What the register tells us

The application was determined in about 11 months. A planning permission on this site expired in June 2017. The scheme has been operating for about 25 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 0.87 MW per turbine on average.