🌬️ Onshore wind farm

Tow Law Wind Farm
County Durham

Recorded in WhichWindTurbine: 3 wind turbines in operation. Point the app at one of them to see its profile in real time.

3
turbines
2.6 MW
MW total
0.9 MW
per turbine

📍 3 turbines mapped — each dot is a turbine recorded in the database. Average position: 54.76195 N · 1.82558 W.

Tow Law Wind Farm

3 turbines · operational · County Durham

Wind farm facts

StatusOperational
County / regionCounty Durham
Turbines3
Installed capacity2.6 MW
Turbine capacity0.9 MW
Tip heightnot recorded
Operator (or applicant)RWE npower
Turbine manufacturernot recorded
Turbine modelnot recorded
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

~2024 reached200020052010201520202025today123
  1. 1Jul 1999 — Application submitted
  2. 2Jun 2000 — Permission granted
  3. 3Dec 2001 — Operational

The register also records a planning permission expiry in Jun 2017, after commissioning: an administrative date with no effect on the operating wind farm, left off the axis.

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2586.

What the register tells us

The application was determined in about 11 months. A planning permission on this site expired in June 2017. The scheme has been operating for about 25 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 0.87 MW per turbine on average.

Nearby

See all wind farms in County Durham.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.