8 turbines · operational · Strathclyde
| Status | Operational |
|---|---|
| County / region | Strathclyde |
| Turbines | 8 |
| Installed capacity | 20 MW |
| Turbine capacity | 2.5 MW |
| Tip height | not recorded |
| Operator (or applicant) | RPMI Railpen (formerly BayWa) |
| Turbine manufacturer | Enercon |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 9 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4073.
The application was determined in about 36 months. Construction to first power took about 40 months. The register records a refusal in March 2013 before the scheme progressed. Permission was ultimately granted on appeal in February 2014. The scheme has been operating for about 6 years. That works out at 2.5 MW per turbine on average.
See all wind farms in Strathclyde.