Tralorg Wind Farm

8 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines8
Installed capacity20 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)RPMI Railpen (formerly BayWa)
Turbine manufacturerEnercon
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 Project timeline Application submitted February 2011 Refused March 2013 Permission granted February 2014 Granted on appeal February 2014 Under construction February 2017 Operational June 2020

From application to operation, this scheme took about 9 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4073.

What the register tells us

The application was determined in about 36 months. Construction to first power took about 40 months. The register records a refusal in March 2013 before the scheme progressed. Permission was ultimately granted on appeal in February 2014. The scheme has been operating for about 6 years. That works out at 2.5 MW per turbine on average.