Tullo Farm

7 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines7
Installed capacity17.5 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)West Coast Energy (agents for Tullo Wind Ltd and GE Wind)
Turbine manufacturerEnercon
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 Project timeline Permission expired June 2003 Application submitted October 2003 Permission granted June 2004 Under construction April 2010 Operational September 2010

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3190.

What the register tells us

The application was determined in about 8 months. Construction to first power took about 5 months. A planning permission on this site expired in June 2003. The scheme has been operating for about 16 years. That works out at 2.5 MW per turbine on average.