Tullo Wind Farm North Extension (Shiels Wind Farm)

3 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines3
Installed capacity7.5 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Eneco
Turbine manufacturerNordex
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 Project timeline Application submitted July 2011 Permission granted February 2012 Under construction April 2013 Operational April 2014

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3818.

What the register tells us

The application was determined in about 7 months. Construction to first power took about 12 months. The scheme has been operating for about 12 years. That works out at 2.5 MW per turbine on average.