Tullo Wind Farm South (Ext.)

4 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines4
Installed capacity10 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Eneco
Turbine manufacturerNordex
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted November 2011 Permission granted September 2012 Under construction May 2013 Operational July 2014 Permission expired September 2018

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4422.

What the register tells us

The application was determined in about 10 months. Construction to first power took about 14 months. A planning permission on this site expired in September 2018. The scheme has been operating for about 12 years. That works out at 2.5 MW per turbine on average.

Nearby

See all wind farms in Grampian.