4 turbines · operational · Grampian
| Status | Operational |
|---|---|
| County / region | Grampian |
| Turbines | 4 |
| Installed capacity | 10 MW |
| Turbine capacity | 2.5 MW |
| Tip height | not recorded |
| Operator (or applicant) | Eneco |
| Turbine manufacturer | Nordex |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 3 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4422.
The application was determined in about 10 months. Construction to first power took about 14 months. A planning permission on this site expired in September 2018. The scheme has been operating for about 12 years. That works out at 2.5 MW per turbine on average.
See all wind farms in Grampian.