7 turbines · operational · Tayside
| Status | Operational |
|---|---|
| County / region | Tayside |
| Turbines | 7 |
| Installed capacity | 14.4 MW |
| Turbine capacity | 2.05 MW |
| Tip height | not recorded |
| Operator (or applicant) | Temporis Capital |
| Turbine manufacturer | Senvion |
| Turbine model | MM92/2050 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 6 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4599.
The application was determined in about 25 months. Construction to first power took about 5 months. The register records a refusal in March 2013 before the scheme progressed. Permission was ultimately granted on appeal in September 2014. A planning permission on this site expired in September 2017. The scheme has been operating for about 8 years. That works out at 2.06 MW per turbine on average.