Tullymurdoch Wind Farm

7 turbines · operational · Tayside

Wind farm facts

StatusOperational
County / regionTayside
Turbines7
Installed capacity14.4 MW
Turbine capacity2.05 MW
Tip heightnot recorded
Operator (or applicant)Temporis Capital
Turbine manufacturerSenvion
Turbine modelMM92/2050

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted August 2012 Refused March 2013 Permission granted September 2014 Granted on appeal September 2014 Under construction August 2017 Permission expired September 2017 Operational January 2018

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4599.

What the register tells us

The application was determined in about 25 months. Construction to first power took about 5 months. The register records a refusal in March 2013 before the scheme progressed. Permission was ultimately granted on appeal in September 2014. A planning permission on this site expired in September 2017. The scheme has been operating for about 8 years. That works out at 2.06 MW per turbine on average.