Twentyshilling Hill Wind Farm

9 turbines · under construction · Dumfries and Galloway

Wind farm facts

StatusUnder Construction
County / regionDumfries and Galloway
Turbines9
Installed capacity37.8 MW
Turbine capacitynot recorded
Tip height82 m
Operator (or applicant)Element Power
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 Scheme REPD 6590 Permission expired December 2012 Application submitted February 2018 Permission granted December 2019 Under construction July 2020 Scheme REPD 4457 Application submitted May 2013 Permission granted July 2015 Permission expired July 2018

The register links a second scheme on this site (REPD ref 4457, Revised): 9 turbines · 3 MW each · applicant Element Power. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 6590.

What the register tells us

The application was determined in about 22 months. A planning permission on this site expired in December 2012. That works out at 4.2 MW per turbine on average.