Twin Rivers

14 turbines · operational · Humberside

Wind farm facts

StatusOperational
County / regionHumberside
Turbines14
Installed capacity28.7 MW
Turbine capacity2.05 MW
Tip heightnot recorded
Operator (or applicant)NTR
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted January 2004 Permission granted January 2009 Permission expired January 2010 Under construction May 2015 Operational August 2016

From application to operation, this scheme took about 12 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3657.

What the register tells us

The application was determined in about 60 months. Construction to first power took about 15 months. A planning permission on this site expired in January 2010. The scheme has been operating for about 10 years. That works out at 2.05 MW per turbine on average.