14
turbines
28.7 MW
MW total
2.05 MW
per turbine

📍 14 turbines mapped — each dot is a turbine recorded in the database. Average position: 53.60873 N · 0.90872 W.

Twin Rivers

14 turbines · operational · Humberside

Wind farm facts

StatusOperational
County / regionHumberside
Turbines14
Installed capacity28.7 MW
Turbine capacity2.05 MW
Tip heightnot recorded
Operator (or applicant)NTR
Turbine manufacturernot recorded
Turbine modelnot recorded
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

→ ~203920052010201520202025today12345
  1. 1Jan 2004 — Application submitted
  2. 2Jan 2009 — Permission granted
  3. 3Jan 2010 — Permission expired
  4. 4May 2015 — Under construction
  5. 5Aug 2016 — Operational

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

From application to operation, this scheme took about 12 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3657.

What the register tells us

The application was determined in about 60 months. Construction to first power took about 15 months. A planning permission on this site expired in January 2010. The scheme has been operating for about 10 years. That works out at 2.05 MW per turbine on average.

Nearby

See all wind farms in Humberside.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.