Wadlow Wind Farm

13 turbines · operational · Cambridgeshire

Wind farm facts

StatusOperational
County / regionCambridgeshire
Turbines13
Installed capacity26 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)DIF
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Project timeline Application submitted May 2006 Refused June 2007 Permission granted November 2009 Granted on appeal November 2009 Under construction August 2011 Operational September 2012 Permission expired November 2015

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3935.

What the register tells us

The application was determined in about 42 months. Construction to first power took about 13 months. The register records a refusal in June 2007 before the scheme progressed. Permission was ultimately granted on appeal in November 2009. A planning permission on this site expired in November 2015. The scheme has been operating for about 14 years. That works out at 2 MW per turbine on average.