🌬️ Onshore wind farm

Wadlow Wind Farm
Cambridgeshire

Recorded in WhichWindTurbine: 13 wind turbines in operation. Point the app at one of them to see its profile in real time.

13
turbines
26 MW
MW total
2 MW
per turbine

📍 13 turbines mapped — each dot is a turbine recorded in the database. Average position: 52.15654 N · 0.30071 E.

Wadlow Wind Farm

13 turbines · operational · Cambridgeshire

Wind farm facts

StatusOperational
County / regionCambridgeshire
Turbines13
Installed capacity26 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)DIF
Turbine manufacturerVestas (secondary source)
Turbine modelV90 (secondary source)
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

○ Cross-checked reference — turbine make and model (secondary source)

Vestas · V90 · 13 turbines · 2 MW each

Source: Wikipedia, list of onshore wind farms in England (compiled from RenewableUK's UKWED and The Wind Power), read on 2026-09-19. This is a compiled list, not a primary record. It is shown because two independent facts — turbine count and rated power — match the database exactly. Awaiting confirmation from a primary source.

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

→ ~20352010201520202025today123456
  1. 1May 2006 — Application submitted
  2. 2Jun 2007 — Refused
  3. 3Nov 2009 — Permission granted
  4. 4Nov 2009 — Granted on appeal
  5. 5Aug 2011 — Under construction
  6. 6Sep 2012 — Operational

The register also records a planning permission expiry in Nov 2015, after construction had started: an administrative date with no effect on the wind farm, left off the axis.

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3935.

What the register tells us

The application was determined in about 42 months. Construction to first power took about 13 months. The register records a refusal in June 2007 before the scheme progressed. Permission was ultimately granted on appeal in November 2009. A planning permission on this site expired in November 2015. The scheme has been operating for about 14 years. That works out at 2 MW per turbine on average.

Nearby

See all wind farms in Cambridgeshire.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.