Wandylaw

10 turbines · operational · Northumberland

Wind farm facts

StatusOperational
County / regionNorthumberland
Turbines10
Installed capacity20.5 MW
Turbine capacity1.95 MW
Tip heightnot recorded
Operator (or applicant)Blue Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 Project timeline Application submitted August 2006 Refused October 2007 Permission granted February 2008 Granted on appeal February 2008 Permission expired February 2011 Under construction May 2012 Operational July 2013

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4250.

What the register tells us

The application was determined in about 18 months. Construction to first power took about 14 months. The register records a refusal in October 2007 before the scheme progressed. Permission was ultimately granted on appeal in February 2008. A planning permission on this site expired in February 2011. The scheme has been operating for about 13 years. That works out at 2.05 MW per turbine on average.