Wardlaw Wood

6 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines6
Installed capacity18 MW
Turbine capacity3 MW
Tip heightnot recorded
Operator (or applicant)Wind Prospect / Community Windpower
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2001 2002 2003 2004 2005 2006 2007 Project timeline Application submitted December 2002 Permission granted September 2003 Operational March 2006

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4691.

What the register tells us

The application was determined in about 9 months. The scheme has been operating for about 20 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 3 MW per turbine on average.