Watford Lodge

5 turbines · operational · Northamptonshire

Wind farm facts

StatusOperational
County / regionNorthamptonshire
Turbines5
Installed capacity12.5 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Broadview Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 Project timeline Application submitted August 2008 Refused April 2011 Permission granted December 2011 Granted on appeal December 2011 Under construction December 2014 Operational November 2015 Permission expired December 2019

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4424.

What the register tells us

The application was determined in about 40 months. Construction to first power took about 11 months. The register records a refusal in April 2011 before the scheme progressed. Permission was ultimately granted on appeal in December 2011. A planning permission on this site expired in December 2019. The scheme has been operating for about 11 years. That works out at 2.5 MW per turbine on average.