Welton Of Creuchies

4 turbines · operational · Tayside

Wind farm facts

StatusOperational
County / regionTayside
Turbines4
Installed capacity9.2 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Green Cat Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Scheme REPD 3396 Application submitted May 2010 Refused March 2011 Permission granted July 2012 Granted on appeal July 2012 Under construction July 2017 Operational January 2018 Scheme REPD 5649 Application submitted September 2015

From application to operation, this scheme took about 8 years.

The register links a second scheme on this site (REPD ref 5649, Application Withdrawn): 4 turbines · 2.3 MW each · 115 m tip height · applicant Private Developer. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3396.

What the register tells us

The application was determined in about 26 months. Construction to first power took about 6 months. The register records a refusal in March 2011 before the scheme progressed. Permission was ultimately granted on appeal in July 2012. The scheme has been operating for about 8 years. That works out at 2.3 MW per turbine on average.