Wern Ddu Wind Farm

4 turbines · operational · Clwyd

Wind farm facts

StatusOperational
County / regionClwyd
Turbines4
Installed capacity9.2 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Tegni
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 Project timeline Application submitted April 2004 Permission granted January 2005 Under construction November 2009 Operational March 2010 Permission expired January 2013

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3592.

What the register tells us

The application was determined in about 9 months. Construction to first power took about 4 months. A planning permission on this site expired in January 2013. The scheme has been operating for about 16 years. That works out at 2.3 MW per turbine on average.