4 turbines · operational · Clwyd
| Status | Operational |
|---|---|
| County / region | Clwyd |
| Turbines | 4 |
| Installed capacity | 9.2 MW |
| Turbine capacity | 2.3 MW |
| Tip height | not recorded |
| Operator (or applicant) | Tegni |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 6 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3592.
The application was determined in about 9 months. Construction to first power took about 4 months. A planning permission on this site expired in January 2013. The scheme has been operating for about 16 years. That works out at 2.3 MW per turbine on average.