West Knock Wind Cluster

3 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines3
Installed capacity2.4 MW
Turbine capacity0.8 MW
Tip heightnot recorded
Operator (or applicant)West Knock Farm
Turbine manufacturerEnercon
Turbine modelE48

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 Project timeline Application submitted July 2009 Permission granted April 2011 Operational October 2011

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3681.

What the register tells us

The application was determined in about 21 months. The scheme has been operating for about 15 years. That works out at 0.8 MW per turbine on average.