1 turbines · operational · Mid Glamorgan
| Status | Operational |
|---|---|
| County / region | Mid Glamorgan |
| Turbines | 1 |
| Installed capacity | 1.5 MW |
| Turbine capacity | 1.5 MW |
| Tip height | 116 m |
| Operator (or applicant) | Infinite Renewables |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 2 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 6079.
The application was determined in about 5 months. Construction to first power took about 2 months. A planning permission on this site expired in July 2019. The scheme has been operating for about 8 years. That works out at 1.5 MW per turbine on average.