Westfield

4 turbines · operational · Fife

Wind farm facts

StatusOperational
County / regionFife
Turbines4
Installed capacity10 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Ventient (formerly Infinis)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 Project timeline Application submitted July 2009 Permission granted June 2012 Under construction July 2012 Operational March 2013

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3684.

What the register tells us

The application was determined in about 35 months. Construction to first power took about 8 months. The scheme has been operating for about 13 years. That works out at 2.5 MW per turbine on average.