5 turbines · operational · Oxfordshire
| Status | Operational |
|---|---|
| County / region | Oxfordshire |
| Turbines | 5 |
| Installed capacity | 6.5 MW |
| Turbine capacity | 1.3 MW |
| Tip height | not recorded |
| Operator (or applicant) | Private Developer |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 8 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3264.
The application was determined in about 58 months. A planning permission on this site expired in July 2016. The scheme has been operating for about 18 years. That works out at 1.3 MW per turbine on average.