Weston Airfield Wind Turbines

2 turbines · operational · Norfolk

Wind farm facts

StatusOperational
County / regionNorfolk
Turbines2
Installed capacity3.6 MW
Turbine capacity1.8 MW
Tip heightnot recorded
Operator (or applicant)Bernard Matthews
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted August 2010 Refused January 2012 Permission granted January 2012 Granted on appeal January 2012 Under construction January 2014 Operational March 2015 Permission expired January 2017

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3354.

What the register tells us

The application was determined in about 17 months. Construction to first power took about 14 months. The register records a refusal in January 2012 before the scheme progressed. Permission was ultimately granted on appeal in January 2012. A planning permission on this site expired in January 2017. The scheme has been operating for about 11 years. That works out at 1.8 MW per turbine on average.