2 turbines · operational · Norfolk
| Status | Operational |
|---|---|
| County / region | Norfolk |
| Turbines | 2 |
| Installed capacity | 3.6 MW |
| Turbine capacity | 1.8 MW |
| Tip height | not recorded |
| Operator (or applicant) | Bernard Matthews |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 5 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3354.
The application was determined in about 17 months. Construction to first power took about 14 months. The register records a refusal in January 2012 before the scheme progressed. Permission was ultimately granted on appeal in January 2012. A planning permission on this site expired in January 2017. The scheme has been operating for about 11 years. That works out at 1.8 MW per turbine on average.