14 turbines · under construction · Strathclyde
| Status | Under Construction |
|---|---|
| County / region | Strathclyde |
| Turbines | 14 |
| Installed capacity | 57 MW |
| Turbine capacity | 4 MW |
| Tip height | 136 m |
| Operator (or applicant) | Thrive Renewables |
| Turbine manufacturer | Siemens Gamesa |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3317.
The application was determined in about 35 months. Permission was ultimately granted on appeal in December 2017. A planning permission on this site expired in December 2022. That works out at 4.07 MW per turbine on average.