Whitemill Wind Farm

7 turbines · operational · Cambridgeshire

Wind farm facts

StatusOperational
County / regionCambridgeshire
Turbines7
Installed capacity14 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Co-operative Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2006 2007 2008 2009 2010 2011 2012 2013 Project timeline Application submitted November 2007 Permission granted November 2008 Operational May 2012

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3480.

What the register tells us

The application was determined in about 12 months. The scheme has been operating for about 14 years. That works out at 2 MW per turbine on average.

Nearby

See all wind farms in Cambridgeshire.