11 turbines · operational · Dumfries and Galloway
| Status | Operational |
|---|---|
| County / region | Dumfries and Galloway |
| Turbines | 11 |
| Installed capacity | 25.3 MW |
| Turbine capacity | 2.3 MW |
| Tip height | not recorded |
| Operator (or applicant) | Whiteside Hill Farm (Scotland) |
| Turbine manufacturer | Vestas |
| Turbine model | GE 2.85-103 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 12 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4502.
The application was determined in about 80 months. Construction to first power took about 27 months. A planning permission on this site expired in February 2018. The scheme has been operating for about 8 years. That works out at 2.3 MW per turbine on average.
See all wind farms in Dumfries and Galloway.