Whittlesey

3 turbines · operational · Cambridgeshire

Wind farm facts

StatusOperational
County / regionCambridgeshire
Turbines3
Installed capacity9 MW
Turbine capacity3 MW
Tip heightnot recorded
Operator (or applicant)REG Windpower (previously Cornwall Light and Power)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2006 2007 2008 2009 Project timeline Application submitted April 2007 Permission granted July 2007 Under construction November 2007 Operational September 2008

From application to operation, this scheme took about 1 year.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3021.

What the register tells us

The application was determined in about 3 months. Construction to first power took about 10 months. The scheme has been operating for about 18 years. That works out at 3 MW per turbine on average.