3 turbines · operational · Cambridgeshire
| Status | Operational |
|---|---|
| County / region | Cambridgeshire |
| Turbines | 3 |
| Installed capacity | 9 MW |
| Turbine capacity | 3 MW |
| Tip height | not recorded |
| Operator (or applicant) | REG Windpower (previously Cornwall Light and Power) |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 1 year.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3021.
The application was determined in about 3 months. Construction to first power took about 10 months. The scheme has been operating for about 18 years. That works out at 3 MW per turbine on average.