20 turbines · under construction · Dumfries and Galloway
| Status | Under Construction |
|---|---|
| County / region | Dumfries and Galloway |
| Turbines | 20 |
| Installed capacity | 87.6 MW |
| Turbine capacity | not recorded |
| Tip height | 180 m |
| Operator (or applicant) | Fred Olsen Renewables |
| Turbine manufacturer | Enercon |
| Turbine model | E-115 EP3 E3 4.200 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4615.
The application was determined in about 51 months. Permission was ultimately granted on appeal in March 2021. A planning permission on this site expired in March 2027. That works out at 4.38 MW per turbine on average.