Windyhill Road (Dunbeg) Wind Farm

14 turbines · operational · Co. Derry / Londonderry

Wind farm facts

StatusOperational
County / regionCo. Derry / Londonderry
Turbines14
Installed capacity42 MW
Turbine capacity3 MW
Tip heightnot recorded
Operator (or applicant)Gaelectric Developments/ CGN Europe Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 Project timeline Application submitted December 2007 Refused March 2010 Permission granted January 2011 Granted on appeal January 2011 Under construction December 2013 Permission expired January 2014 Operational November 2014

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4142.

What the register tells us

The application was determined in about 37 months. Construction to first power took about 11 months. The register records a refusal in March 2010 before the scheme progressed. Permission was ultimately granted on appeal in January 2011. A planning permission on this site expired in January 2014. The scheme has been operating for about 12 years. That works out at 3 MW per turbine on average.