Winscales Moor

7 turbines · operational · Cumbria

Wind farm facts

StatusOperational
County / regionCumbria
Turbines7
Installed capacity6 MW
Turbine capacity0.85 MW
Tip heightnot recorded
Operator (or applicant)Gravis Capital Management
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 Project timeline Application submitted October 2006 Permission granted June 2007 Under construction December 2008 Operational May 2009

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2986.

What the register tells us

The application was determined in about 8 months. Construction to first power took about 5 months. The scheme has been operating for about 17 years. That works out at 0.86 MW per turbine on average.