Winscales Phase I and II

11 turbines · operational · Cumbria

Wind farm facts

StatusOperational
County / regionCumbria
Turbines11
Installed capacity8.8 MW
Turbine capacity0.8 MW
Tip heightnot recorded
Operator (or applicant)Cumbria Wind Farms
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 Project timeline Application submitted November 1997 Permission granted June 1999 Operational December 2004

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3492.

What the register tells us

The application was determined in about 19 months. The scheme has been operating for about 22 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 0.8 MW per turbine on average.