Winwick

6 turbines · operational · Northamptonshire

Wind farm facts

StatusOperational
County / regionNorthamptonshire
Turbines6
Installed capacity12.3 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Blue Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted May 2010 Refused July 2012 Permission granted July 2012 Granted on appeal July 2012 Under construction April 2015 Operational June 2016 Permission expired July 2017

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4164.

What the register tells us

The application was determined in about 26 months. Construction to first power took about 14 months. The register records a refusal in July 2012 before the scheme progressed. Permission was ultimately granted on appeal in July 2012. A planning permission on this site expired in July 2017. The scheme has been operating for about 10 years. That works out at 2.05 MW per turbine on average.