Withernwick extension

9 turbines · operational · Humberside

Wind farm facts

StatusOperational
County / regionHumberside
Turbines9
Installed capacity18 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Energiekontor UK
Turbine manufacturerSenvion
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 Original scheme Application submitted April 2008 Permission granted September 2008 Permission expired September 2011 Under construction April 2012 Operational March 2013 Later scheme Application submitted June 2014 Refused June 2015 Permission granted December 2016 Granted on appeal December 2016 Under construction September 2018 Permission expired December 2018 Operational August 2019

From application to operation, this scheme took about 5 years.

The register links a second scheme on this site (REPD ref 4432, Operational): 4 turbines · 2.05 MW each · applicant Energiekontor UK. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3987.

What the register tells us

The application was determined in about 5 months. Construction to first power took about 11 months. A planning permission on this site expired in September 2011. The scheme has been operating for about 13 years. That works out at 2 MW per turbine on average.

Nearby

See all wind farms in Humberside.