🌬️ Onshore wind farm

Withernwick extension
Humberside

Recorded in WhichWindTurbine: 9 wind turbines in operation. Point the app at one of them to see its profile in real time.

9
turbines
18 MW
MW total
2 MW
per turbine

📍 4 turbines mapped — each dot is a turbine recorded in the database. Average position: 53.85806 N · 0.16296 W.

Withernwick extension

9 turbines · operational · Humberside

Wind farm facts

StatusOperational
County / regionHumberside
Turbines9
Installed capacity18 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Energiekontor UK
Turbine manufacturerSenvion
Turbine modelnot recorded
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

→ ~2042201620182020202220242026today123456
  1. 1Jun 2014 — Application submitted
  2. 2Jun 2015 — Refused
  3. 3Dec 2016 — Permission granted
  4. 4Dec 2016 — Granted on appeal
  5. 5Sep 2018 — Under construction
  6. 6Aug 2019 — Operational

The register also records a planning permission expiry in Dec 2018, after construction had started: an administrative date with no effect on the wind farm, left off the axis.

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

From application to operation, this scheme took about 5 years.

The register links a second scheme on this site (REPD ref 4432, Operational): 4 turbines · 2.05 MW each · applicant Energiekontor UK. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3987.

What the register tells us

The application was determined in about 5 months. Construction to first power took about 11 months. A planning permission on this site expired in September 2011. The scheme has been operating for about 13 years. That works out at 2 MW per turbine on average.

Nearby

See all wind farms in Humberside.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.