Woodlands Barton Wind Project

2 turbines · operational · Cornwall

Wind farm facts

StatusOperational
County / regionCornwall
Turbines2
Installed capacity4.6 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Private Developer
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 Project timeline Application submitted November 2012 Permission granted February 2013 Permission expired February 2014 Under construction May 2014 Operational September 2014

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4140.

What the register tells us

The application was determined in about 3 months. Construction to first power took about 4 months. A planning permission on this site expired in February 2014. The scheme has been operating for about 12 years. That works out at 2.3 MW per turbine on average.