🌬️ Onshore wind farm

Woodlands Barton Wind Project
Cornwall

Recorded in WhichWindTurbine: 2 wind turbines in operation. Point the app at one of them to see its profile in real time.

2
turbines
4.6 MW
MW total
2.3 MW
per turbine

📍 2 turbines mapped — each dot is a turbine recorded in the database. Average position: 50.42529 N · 4.81427 W.

Woodlands Barton Wind Project

2 turbines · operational · Cornwall

Wind farm facts

StatusOperational
County / regionCornwall
Turbines2
Installed capacity4.6 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Private Developer
Turbine manufacturernot recorded
Turbine modelnot recorded
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

→ ~2037201520202025today12345
  1. 1Nov 2012 — Application submitted
  2. 2Feb 2013 — Permission granted
  3. 3Feb 2014 — Permission expired
  4. 4May 2014 — Under construction
  5. 5Sep 2014 — Operational

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4140.

What the register tells us

The application was determined in about 3 months. Construction to first power took about 4 months. A planning permission on this site expired in February 2014. The scheme has been operating for about 12 years. That works out at 2.3 MW per turbine on average.

Nearby

See all wind farms in Cornwall.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.