Woodlands Wind Farm

3 turbines · operational · Lanarkshire

Wind farm facts

StatusOperational
County / regionLanarkshire
Turbines3
Installed capacity2.6 MW
Turbine capacity0.85 MW
Tip height70 m
Operator (or applicant)WhiteRock Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted March 2012 Permission expired July 2012 Permission granted July 2013 Under construction March 2016 Operational July 2016

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 6173.

What the register tells us

The application was determined in about 16 months. Construction to first power took about 4 months. A planning permission on this site expired in July 2012. The scheme has been operating for about 10 years. That works out at 0.87 MW per turbine on average.