Woolley Hill Wind Farm

4 turbines · operational · Cambridgeshire

Wind farm facts

StatusOperational
County / regionCambridgeshire
Turbines4
Installed capacity10 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Aviva
Turbine manufacturerNordex
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2009 2010 2011 2012 2013 2014 2015 Project timeline Application submitted November 2010 Permission expired March 2011 Refused July 2011 Permission granted March 2012 Granted on appeal March 2012 Under construction March 2014 Operational April 2014

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4175.

What the register tells us

The application was determined in about 16 months. Construction to first power took about 1 month. The register records a refusal in July 2011 before the scheme progressed. Permission was ultimately granted on appeal in March 2012. A planning permission on this site expired in March 2011. The scheme has been operating for about 12 years. That works out at 2.5 MW per turbine on average.