Worksop - B&Q

1 turbines · operational · Nottinghamshire

Wind farm facts

StatusOperational
County / regionNottinghamshire
Turbines1
Installed capacity2 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Ecotricity
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted September 2007 Permission granted November 2007 Under construction December 2008 Operational January 2009 Permission expired November 2017

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3510.

What the register tells us

The application was determined in about 2 months. Construction to first power took about 1 month. A planning permission on this site expired in November 2017. The scheme has been operating for about 17 years. That works out at 2 MW per turbine on average.