13 turbines · operational · Cambridgeshire
| Status | Operational |
|---|---|
| County / region | Cambridgeshire |
| Turbines | 13 |
| Installed capacity | 26 MW |
| Turbine capacity | 2 MW |
| Tip height | 100 m |
| Operator (or applicant) | Renewable Energy Systems (RES) |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 10 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4248.
The application was determined in about 45 months. Construction to first power took about 17 months. The register records a refusal in October 2008 before the scheme progressed. Permission was ultimately granted on appeal in April 2010. The scheme has been operating for about 10 years. That works out at 2 MW per turbine on average.