Yonderton Farm

2 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines2
Installed capacity1 MW
Turbine capacity0.5 MW
Tip heightnot recorded
Operator (or applicant)Green Cat Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2009 2010 2011 2012 2013 2014 2015 Scheme REPD 3723 Application submitted May 2010 Permission granted July 2010 Under construction August 2014 Operational December 2014 Scheme REPD 3654 Application submitted September 2011 Refused August 2012

From application to operation, this scheme took about 4 years.

The register links a second scheme on this site (REPD ref 3654, Application Refused): 1 turbines · 1 MW each · applicant J & G Energy Ltd. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3723.

What the register tells us

The application was determined in about 2 months. Construction to first power took about 4 months. The scheme has been operating for about 12 years. That works out at 0.5 MW per turbine on average.