A'Chruach (Phase 1)

21 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines21
Installed capacity48.3 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Infinis (formerly Novera Energy)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted December 2011 Permission granted June 2012 Under construction June 2015 Operational June 2016

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4331.

What the register tells us

The application was determined in about 6 months. Construction to first power took about 12 months. The scheme has been operating for about 10 years. That works out at 2.3 MW per turbine on average.