Aikengall IIa Community Wind Farm

19 turbines · operational · Borders

Wind farm facts

StatusOperational
County / regionBorders
Turbines19
Installed capacity81.7 MW
Turbine capacity4.3 MW
Tip height145 m
Operator (or applicant)Community Windpower
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 Project timeline Permission expired October 2011 Application submitted February 2014 Permission granted October 2016 Granted on appeal October 2016 Under construction January 2021 Operational November 2021

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4591.

What the register tells us

The application was determined in about 32 months. Construction to first power took about 10 months. Permission was ultimately granted on appeal in October 2016. A planning permission on this site expired in October 2011. The scheme has been operating for about 5 years. That works out at 4.3 MW per turbine on average.