Airies Farm

14 turbines · operational · Dumfries and Galloway

Wind farm facts

StatusOperational
County / regionDumfries and Galloway
Turbines14
Installed capacity35 MW
Turbine capacity2.5 MW
Tip height137 m
Operator (or applicant)NTR
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted August 2012 Permission granted March 2013 Permission expired March 2014 Under construction February 2016 Operational March 2017

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4462.

What the register tells us

The application was determined in about 7 months. Construction to first power took about 13 months. A planning permission on this site expired in March 2014. The scheme has been operating for about 9 years. That works out at 2.5 MW per turbine on average.